Sixth Ring Road 184

Project Details

Construction, completion and maintenance of the interchanges of the main highways (Sixth Ring Road) connecting to new housing area at South Jahra, area numbers 1 – 3 – 4 – 5 and 7

Owner: Ministry of Public Works

Project Value: KD 39,370,000/- (Equivalent US$ 140,157,200/-)

Duration: 1095 days

Start Date: 06/11/2010

End Date: 05/11/2013

Project Status: Completed

Extended Date 01/01/0001